|
CAPITAL PROJECTS
PROGRESS – 7th May 2008
Isn’t it always the way? You think you are past all your big problems
and are on a nice straight easy run for a while and WHAM, you run into
another big one!
Having reached the top of La Vallee we were all
looking forward to getting out of the road and to a nice easy run through the
grounds of the school and the Vallee Gardens,
when a rather strange and unknown Victorian brick culvert made its
appearance, leaking like a sieve and pouring clean water into the trench. No
one seemed to know where it was coming from or going to, except that the
water appeared to end up in the little stream running in front of the houses.
It had to go, as it was directly in the way of the new sewer, and when it was
broken and the water was being pumped away the little stream stopped – which
rather upset one or two residents. Further excavation revealed that there
were apparently TWO culverts, one of which is dry, and then, of all things, a
well was discovered, which had been covered over by the road and which
apparently was once the source of supply to the nearby cattle trough. The
good news was that when the trench was backfilled with a layer of stone the
water found its way back into the stream again. The bad news was that the
ground was so poor that the trench collapsed and caused severe damage to the
newly installed manhole.
However, as someone said, there is no such thing as problems, only
solutions, and of course a solution was found by the very competent
contractor and the work of laying the sewer pipes is continuing into the
school grounds and on into the Gardens. The damaged manhole will be repaired
in situ in a week or so.
The cobbled road to Platte Saline has been re-cobbled and looks very
smart, and we are getting near the end of the disruptive part of the job now,
though it is not quite clear yet. Over the next three or four weeks the
trench in Vallee will be partially reopened, the
electric cable will be laid, the trench backfilled again, and then probably
starting on 19 May Ronez will come along with
tarmac – and that should see the roads back to normal. There will still be
some heavy traffic moving about so caution is still required.

Dare it be said? With hopefully no more unforeseen obstructions, it is
anticipated that the project will be completed in early June.
At the Courthouse the work of renovating the Court building itself is
going well. The additional electrical work is largely complete and the
specialist equipment supplier is expected shortly to install and commission
the equipment. Scaffolding removal still seems to be a bit of a problem but
hopefully by the time this appears it will be done. There is still quite a
lot of painting to complete – it is a pretty big building – but it is
“getting there”, and then there is the carpeting. When finished, which should
not now be too long, it will be a smart looking building, inside and
out.

|
|
Notice of Road
Closures – Vallee Sewer.
The
work of renewing the main sewer is now advancing onto the public highways
which will involve closure of roads to ensure safety during the construction
works.
Commencing
from Tuesday 8th January 2008 Crabby Road will be closed to
through traffic until approximately the end of February. Initially the road
will be closed at a point just above the hospital entrance (at the top of the
cobbled road leading to Fort Doyle), and the point of closure will be moved
towards La Vallee junction as the work progresses.
Access
will only be allowed to properties along Crabby Road itself, and then this
will be limited to pedestrian access whilst the work is underway adjacent to
that property.
Further
closures will be necessary at a future date. Advance notice will be given as
soon as practical.
Please
also note that the dirt road along Platte Saline in front of the houses is a
private road and this is not an alternative route.
Thank
you for your co-operation in this matter.
Julie Turner
States Engineer
|